Preparation for steel structure installation of prefab industrial buildings

Time:[2022-3-14]  Hits:2527

With the continuous development of economy, diversified architectural structures have entered our daily life. Develop prefabricated buildings such as prefabricated concrete structure, steel structure and modern wood structure according to local conditions. Steel structure prefabricated buildings are widely used in different types of fields such as industry, commerce, agriculture and so on. The fast installation method is conducive to the rapid completion of the industry and get a good development trend.

The contents and requirements of steel structure installation preparation of prefab industrial buildings are the same as those of ordinary steel structure installation works. During the construction of steel column foundation, the positioning and protection of anchor bolts shall be done well, and the top elevation of foundation and anchor bolts shall be controlled. After foundation construction, inspection and acceptance shall be carried out according to the following contents:

(1) Whether the axis position of each row and column is correct;

(2) Whether the span of each span meets the design requirements;

(3) Whether the elevation of foundation top meets the design requirements;

(4) Whether the position and elevation of anchor bolts meet the design and specification requirements.

Before the hoisting of components, the shape and section geometric dimensions of components shall be inspected according to the relevant provisions in the <<Code for construction and acceptance of steel structure engineering>> and the deviation shall not exceed the value specified in the specification; The components shall be numbered according to the requirements of the design drawings, highlighting the installation center mark. The center mark and elevation mark in two directions shall be popped up for the steel column; Mark the position of binding point; The length of the column should be measured, and the length error should be recorded in detail. It should be written on the plane beside the center mark of the lower part of the column with oil pen, so that it can be adjusted in the two grouting layer of the top elevation of the foundation.

Components entering the construction site must have quality assurance and detailed acceptance records; It shall be stacked in the designated area according to the type, model and installation sequence of components. Enough supporting surface shall be provided for the component stratum skid to prevent the fulcrum from sinking; When components of the same model are stacked, the fulcrum of each layer of components shall be on the same straight line; The deformed components shall be corrected in time and can be installed only after passing the inspection.

Following the contents of the specification, the construction party effectively prepares for installation and provides favorable conditions for the installation of the main steel structure of the prefab industrial buildings. For the construction of steel column foundation, implement the work details and do the work well, which is more conducive to the later installation of steel structure. The normal use of prefab industrial buildings is closely related to the installation preparation. Relevant construction party shall make preparations for the installation of prefab industrial buildings.

Copyright:佛山市勝邦鋼結構有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粵ICP備13078463號
主站蜘蛛池模板: 日韩视频高清免费看 | 一本岛高清v不卡免费一三区 | 一区二区不卡在线观看 | 日韩免费在线观看视频 | 日本 毛片基地-亚洲 | 在线片视频网站 | 中文字幕视频在线观看 | 综合亚洲网 | 不卡一区在线观看 | 婷婷激情狠狠综合五月 | 亚洲婷婷六月 | 视频在线二区 | 亚洲最新中文字幕 | 伊人三级 | 在线视频一区二区三区 | 2021免费日韩视频网 | 青青草视频在线观看 | 久久免 | 日韩手机专区 | 福利社在线观看 | 最近最中文字幕视频 | 抽搐一进一出gif免费动态 | 女人扒开 | freexxx性欧美孕交孕妇 | 在线老司机| 99资源在线 | 色婷婷激婷婷深爱五月小说 | 最新韩国伦理片大全手机在线播放 | 久久国产精品偷 | 天天插天天操天天干 | 色综合久久天天综线观看 | 小草青青神马影院 | 天天天操 | 成人在线中文字幕 | 农村新婚处破女小说 | 午夜性色福利视频 | 麻豆高清视频在线观看 | 开小箩莉嫩苞h嗯嗯好疼小说 | 欧美一区2区三区4区公司 | 久久最新免费视频 | a天堂一码二码专区 |