Preparation for steel structure installation of prefab industrial buildings

Time:[2022-3-14]  Hits:2740

With the continuous development of economy, diversified architectural structures have entered our daily life. Develop prefabricated buildings such as prefabricated concrete structure, steel structure and modern wood structure according to local conditions. Steel structure prefabricated buildings are widely used in different types of fields such as industry, commerce, agriculture and so on. The fast installation method is conducive to the rapid completion of the industry and get a good development trend.

The contents and requirements of steel structure installation preparation of prefab industrial buildings are the same as those of ordinary steel structure installation works. During the construction of steel column foundation, the positioning and protection of anchor bolts shall be done well, and the top elevation of foundation and anchor bolts shall be controlled. After foundation construction, inspection and acceptance shall be carried out according to the following contents:

(1) Whether the axis position of each row and column is correct;

(2) Whether the span of each span meets the design requirements;

(3) Whether the elevation of foundation top meets the design requirements;

(4) Whether the position and elevation of anchor bolts meet the design and specification requirements.

Before the hoisting of components, the shape and section geometric dimensions of components shall be inspected according to the relevant provisions in the <<Code for construction and acceptance of steel structure engineering>> and the deviation shall not exceed the value specified in the specification; The components shall be numbered according to the requirements of the design drawings, highlighting the installation center mark. The center mark and elevation mark in two directions shall be popped up for the steel column; Mark the position of binding point; The length of the column should be measured, and the length error should be recorded in detail. It should be written on the plane beside the center mark of the lower part of the column with oil pen, so that it can be adjusted in the two grouting layer of the top elevation of the foundation.

Components entering the construction site must have quality assurance and detailed acceptance records; It shall be stacked in the designated area according to the type, model and installation sequence of components. Enough supporting surface shall be provided for the component stratum skid to prevent the fulcrum from sinking; When components of the same model are stacked, the fulcrum of each layer of components shall be on the same straight line; The deformed components shall be corrected in time and can be installed only after passing the inspection.

Following the contents of the specification, the construction party effectively prepares for installation and provides favorable conditions for the installation of the main steel structure of the prefab industrial buildings. For the construction of steel column foundation, implement the work details and do the work well, which is more conducive to the later installation of steel structure. The normal use of prefab industrial buildings is closely related to the installation preparation. Relevant construction party shall make preparations for the installation of prefab industrial buildings.

Copyright:佛山市勝邦鋼結構有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粵ICP備13078463號
主站蜘蛛池模板: 铨盛国际供应链-PC增韧剂/硅系增韧剂/耐寒增韧剂/耐化学增韧剂 | 履带吊出租_大型吊装设备_履带式起重机-山东腾飞吊装工程有限公司 | 南京仁康体检--南京仁康门诊部有限公司| 无塔供水_全自动无塔供水设备_石家庄工泉水处理_无塔供水器 | 全功能护理训练模拟人-创伤护理人-高级电脑心肺复苏模型-上海康季 | 英格索兰隔膜泵_ARO气动隔膜泵_英格索兰隔膜泵配件【原厂正品】连续五年无投诉_英格索兰隔膜泵代理-苏州瑞晟茂环保设备有限公司 印刷公司,北京印刷厂,宣传画册手册印刷厂-和智印彩页设计 | 自动门、旋转门、速通门维修保养升级服务平台_门道佰分佰【官网】 | 制砂机-合金-耐磨锤头-耐磨衬板-铸造件厂家-巩义市豫园宏宇铸造有限公司 | 浙江桥梁检测车出租_杭州桥检车出租_桥梁检测车出租_桥检车租赁_桥梁检测车租赁-广州众诚设备租赁有限公司 | 模温机_厂家_现货供应-卡塞尔机械(浙江)有限公司 | 深圳市大业激光成型技术有限公司| 泡沫混凝土垫层填充厂家,发泡混凝土垫层填充,轻质混凝土垫层填充厂家,深圳市鸿奥建材发展有限公司 | 景德镇市奥群包装材料有限公司| 湖州网站建设_湖州网络公司_湖州后普网络科技有限公司 | 珠海希玛林顺潮眼科医院| 智能灰熔融性测试仪,微机自动定硫仪,快速自动测硫仪-鹤壁市恒科仪器仪表有限公司 | 苏州妙凯电子有限公司-供应军工电源芯片|线性恒流IC|开关电源IC|LED驱动芯片|MOS管|IPM|IGBT|MCU开发|电源模块 | 耐磨涂料_陶瓷涂料_高温涂料_高硬度耐磨涂料-北京耐默科技 | 王者荣耀/和平精英扫码上号登录器_微信安卓苹果扫码上号登录软件 - 上号宝扫码登录器 | 气泡式洗菜机-气泡喷淋清洗机-喷淋清洗风干线-诸城市迪凯工业装备有限公司 | 以物联网技术为核心专注于智能安防领域物联网服务的高新技术企业-北京欣智恒科技股份有限公司(官网) | 西安外墙防水补漏-堵漏-防腐-保温工程公司-陕西宏图祥瑞实业有限公司 | 冷却特性测试仪_ 刀柄热胀仪_加油小车价格_皮带张力仪_上海川奇机电设备有限公司 | 人民交通网-人民交通杂志官网| 清洗剂-防锈油-润滑油-嘉信供应链一站式供应厂家 | 住友套管总代理-日本住友套管-住友热缩管-上海弘奇电子科技有限公司 | 青岛熔喷过滤芯_青岛过滤器生产厂家_青岛净水滤料厂家_青岛净达过滤技术有限公司 | 远红外桑拿房-江苏侨达健康科技有限公司| 思为网络_成都百度优化快照排名-成都网站建设优化_成都网页设计_成都SEO公司 | 西安外墙防水补漏-堵漏-防腐-保温工程公司-陕西宏图祥瑞实业有限公司 | 河北伟业波纹管-百顺牌波纹补偿器(波纹管,膨胀节,伸缩节)、非金属补偿器 | 永磁变频空压机_青岛空压机_螺杆空压机_口罩专用空压机-青岛凯瑞特机电设备有限公司 | 渣浆泵厂家/潜水-渣浆泵过流件-管道增压泵 - 河北聚洪泵业有限公司 | 网带窑,催化剂网带窑,电热回转窑-淄博圣元窑炉工程有限公司 | 南通搬运公司|吊车租赁|大件吊装|设备搬运|工厂搬迁|起重吊装搬运-顺林搬运 | 行星式球磨机-实验室球磨仪[东方天净]小型高能研磨筛分仪直销厂家 | 机锋网-畅享科技品质生活,尽在机锋网 | 上海教师招聘考试网_上海编制教师招聘网 | 模具水垢清洗机_模具管路清洗机_模具专用清洗机-苏州意德特机械有限公司 | 上海舞台灯光音响租赁搭建线阵_年会演出摇头光束面光灯出租_led电子显示屏出租-上海led大屏幕租赁 | 齐东汽车-提供抑尘车|洒水车|压缩垃圾车|餐厨垃圾车|垃圾转运车|清洗吸污车|扫路车价格,图片及视频 |