Winter construction measures for metal workshop building

Time:[2021-11-24]  Hits:2731

a. The winter construction of steel structure production and installation shall be carried out strictly in accordance with the relevant steel structure winter construction regulations.

b. When steel components are installed at positive temperature and at negative temperature, the shrinkage of components should be considered according to the difference in ambient temperature, and technical measures to adjust deviation should be taken during construction.

c. Welders who participate in the construction of negative temperature steel structures should undergo negative temperature welding process training, pass the examination, and obtain corresponding certificates.

d. The steel and related connecting materials used under negative temperature must be accompanied by a quality certificate, and the performance meets the requirements of the design and product standards.

e. The welding rod used under negative temperature shall not be exposed for more than 2 hours, and it shall be re-baked after more than 2 hours, and the number of baking of the welding rod shall not exceed 3 times.


f. Bake the flux according to the regulations before use, so that the water content does not exceed 0.1%.

g. High-strength bolts used under negative temperature must have a product certificate, and the torque coefficient and axial force must be re-inspected under negative temperature.

h. The paint used for steel structure under negative temperature shall not use water-based paint.

i. When the component is blanked, a shrinkage margin should be reserved, and the welding shrinkage and compression deformation should be coordinated with the shrinkage deformation of the steel under negative temperature.

j. When assembling the components, expand the assembly from the inside to the outside according to the order stipulated by the process, and do a test during the assembly of the negative temperature to determine the shrinkage value of the weld that needs to be reserved.

k. When assembling components, remove rust, burrs, soil, oil, ice and snow and other debris remaining in the joint 50mm, and keep the joints dry and free of residual moisture.

l. Multi-layer welding should be used when welding steel plates above 9mm under negative temperature. The welds should be welded layer by layer from bottom to top. Each weld is completed at a time. If the welding is interrupted, the welding defects should be removed before welding again. It is strictly forbidden to start the arc on the welding base metal.

m. When the steel structure is installed on site, in case of snow or wind speed above 6m/s, set up a protective shed.

n. The unqualified welds shall be removed and re-welded, and the welding shall be carried out in accordance with the provisions of the welding process of the steel structure under negative temperature.

o. When the ambient temperature is lower than 0°C, perform the painting process test before applying the anti-corrosion coating. When painting, the rust, oil stains, burrs, etc. on the surface of the component must be cleaned up, and the surface must be kept dry. No painting work is allowed in snowy weather or when there is thin ice on the components.

p. Take anti-skid measures when transporting and stacking steel structures in winter. The component stacking site is flat and solid without puddles, and the ground is free of icing. When the components of the same model are stacked, the components should be kept horizontal, and the shims should be placed on the same vertical line to prevent the components from slipping.

q. Before the steel structure is installed, its quality shall be re-inspected according to the requirements under negative temperature conditions, and the components that have been missed in the production and deformed during transportation and stacking shall be repaired and corrected on the ground.

r. When using steel cables to hoist steel components, anti-skid spacers should be added, the gusset plate that is hoisted at the same time as the components, and the fixtures required by the installer should be tied firmly with ropes.

s. According to the temperature conditions, the steel component installation sequence chart is compiled, and the installation shall be carried out in strict accordance with the specified sequence during construction.

t. Prepare the welding process for steel structure installation, and both ends of a component shall not be welded at the same time.

u. Before installation, remove ice, snow and dew on the surface of the components, but do not damage the coating.

v. Columns and main beams installed at negative temperature shall be corrected immediately, and the correct position shall be immediately fixed permanently. The components installed on the same day shall form a stable space system.

w. When installing high-strength bolt joints, there must be no snow or ice on the friction surface of the components, and no contact with dirt, oil and other stolen objects.

x.In addition to complying with the requirements of "Code for Construction and Acceptance of Steel Structure Engineering" (GB50250-95), the quality of steel structure installation under negative temperature should also be inspected and accepted according to design requirements.

Copyright:佛山市勝邦鋼結構有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粵ICP備13078463號
主站蜘蛛池模板: 新硕考研_新硕寄宿考研-升学路上的规划师【官网】 | 天津佳创博为科技有限公司|AGV控制器|无人搬运车|磁导航传感器|AGV专业零配件 | 消字号牙膏代加工|面膜代加工|凝胶贴牌|漱口水贴牌-南京三盾药业有限公司-消字号牙膏代加工|面膜代加工|凝胶贴牌|漱口水贴牌-南京三盾药业有限公司 | 潍坊沃林机械设备有限公司-牵引式风送果园打药机,悬挂式风送果园喷雾机,自走式果树喷药机,车载式风送远程喷雾机-潍坊沃林机械设备有限公司-牵引式风送果园打药机,悬挂式风送果园喷雾机,自走式果树喷药机,车载式风送远程喷雾机 潍坊网络推广,临沂360推广,东营360推广,枣庄360推广,潍坊网站建设,潍坊网络公司,潍坊360搜索,潍坊APP开发,潍坊360推广,潍坊360代理,潍坊点睛网络科技有限公司 | 苏州拆除公司_太仓拆除公司_常熟拆除公司_昆山拆除公司--苏州伊诺尔拆除工程有限公司 | 景德镇芳然装饰有限公司| 真空系统,真空泵租赁技术服务-兆德机械(上海)有限公司 | 围墙护栏,护栏网,围栏,锌钢栅栏,护栏网厂家--安平县沃达金属丝网制造有限公司 | 液晶拼接屏_三星46寸/55寸/LG液晶拼接屏_深圳拼接墙厂家_电视大屏幕液晶拼接_高清工业级液晶监视器 | 名片印刷,名片制作,名片设计,印刷彩色名片,数码快印名片-北京瑞思凯信息咨询公司 | 郑州天恩石油机械有限公司| 逍遥安卓模拟器_安卓模拟器电脑版_安卓手游模拟器哪个好用_逍遥手机模拟器官网 | 上饶环亚电脑会计培训学校--电脑学校|上饶电脑学校|上饶电脑培训|会计培训|上饶会计培训|上饶县会计培训|广丰会计培训|玉山会计培训|横峰会计培训|上饶网店培训 上进电缆(嘉兴)股份有限公司官网 - 光伏电缆|防火电缆|电力电缆|铝合金电缆专业生产厂家 | 墙板_户外墙板_ASA共挤户外墙板-康亿家生态木业集团 | 趣看科技-视频新媒体技术一体化专业服务商 | 上海网站建设公司|上海自适应网站制作|上海仿制网站建设公司-智淇网络 | 江苏苏仪集团有限公司 江苏红光仪表厂有限公司 | 消防水电施工,消防水电安装,消防水电施工公司,消防水电改造-亿杰北京消防工程公司 | 太原门禁系统_太原车牌识别_山西人脸识别系统-山西元一智能科技有限公司 | 螺杆式空压机|沈阳螺杆空压机厂家推荐选择沈阳隆瑚机械有限公司 螺带混合机|卧式螺带混合机|双动力混合机-无锡鑫海干燥粉体设备有限公司 | 西安网站建设,西安网站设计制作,西安短视频拍摄_短视频运营就选动力无限网络推广公司 | 潍坊亿宏重工机械有限公司,破碎机,高性能立磨机,颚式破碎机,锤式破碎机反击式破碎机,重锤式破碎机,高性能反击式破碎机,圆锥式破碎机,给料机系列,链板给料机系列,简易给料机系列,振动给料机 | 上海消防器材|水雾喷头|水幕喷头|螺旋喷头|雾化喷头|泡沫喷头 - 上海舜丹消防设备有限公司 | 昆明护栏网厂家_隔离栅_围栏网_石笼网「13年生产经验」-云南北辛商贸 | 箱式电炉,箱式烧结炉,箱式马弗炉,箱式实验炉,高温箱式电阻炉,箱式加热炉,箱式退火炉,箱式真空气氛炉洛阳研博炉业有限公司 | 长春试验机-长春凯新试验仪器_试验机研发生产 专注试验机_首页 | 四川杨氏达防水材料有限公司 | 三次元振动研磨机|涡流光饰机|东莞市正雄研磨机械有限公司 | 上海办公家具_高端实木办公家具_现代智能办公家具定制厂-上海迈亚家具有限公司 | 微波烘干设备厂家-微波烘干干燥设备-山东邦普机械设备有限公司 | 天然气车船展、氢能装备展、氢燃料汽车展、核电装备展、国防信息化装备展---北京企发展览服务有限公司 | 自走式缠绕机_上海德目包装设备厂家_在线式缠绕机_缠绕膜打包机 自装卸(挂桶)车|钩臂垃圾车|压缩垃圾车|密封自卸车|环卫垃圾车|餐厨车泔水车湖北程力专用车厂家 | 长沙网站建设,网站设计制作,长沙小程序开发,公众号开发,长沙叶老设计 | 兰州职业学校-新华互联网学校咨询平台中心 | 万级无菌室-阳性对照室-干细胞实验室-广州沃霖实验室设备有限公司 | 上海中医医院_上海名老中医专家门诊_上海徐浦中医医院 | 液压万能试验机价格_电子万能试验机|摩擦磨损试验机厂家-济南辰达试验机制造有限公司 | 液压油缸_液压系统_液压泵站生产厂家-浙江汉达机械专注液压行业21年 | 自动锁螺丝机_在线式拧螺丝机_自动化灌胶机_ab点胶机_品牌厂家 | 展馆展厅设计_数字多媒体展厅_3D全息投影_三维动画制作_企业宣传片|深圳市华南数字科技有限公司 斩天手游网_高质量手机游戏下载中心 | 样品前处理仪器_光谱仪器_色谱/分析仪器_测量/计量仪器_青岛聚创世纪环保科技有限公司 |